PA Turnpike / I-95 Interchange Project

Road Detours

Ford Road Bridge Detour to begin July 9, 2012

 

The first stage of the Interchange Project consists of nine construction projects, which will
continue through 2017.

Planned Construction

Section B - Mainline Toll Plaza in Bensalem - 2013-2015
Section D1/E - Turnpike/I-95 Interchange /East Turnpike Widening to Delaware River Bridge -
2013-2016

Section D2/F - Turnpike/I-95 Interchange/ Interstate 95 South to PA 413 - 2014-2017

Current Construction

Section S2 - S.R. 2035 Bridge (Richlieu Road) - 2012-2013
Section S3 - S.R. 2192 Bridge (Ford Road) - 2012-2013
Advanced ITS - 2012-2013

Completed Construction

Section S1 - S.R. 2023 Bridge (Galloway Road) - Nov. 15, 2010 - Nov. 2011
Section S1 - S.R. 2029 Bridge (Bristol-Oxford Valley Road) - Oct. 25, 2010 - Nov. 2011
I-95 Wetland Mitigation Site - 2012